Why have a variations power?



At common law, the principal does not have an automatic right to instruct variations.

Unless the
contract specifically empowers the principal to instruct variations, the contractor can refuse to perform the variation and insist on performing its original scope of works. This is true of all types of variations, including increases to, decreases from, or qualitative changes to, the contractor's scope of works.

This principle applies to all contracts, including
subcontracts and consultants' agreements. It is therefore normal for construction related contracts to have a clause specifically empowering the principal to instruct variations.

If the principal insists on a variation without the right to do so, the consequences can be serious. The instruction will constitute a
breach of contract and, if the breach is sufficiently serious, may entitle the contractor to terminate the contract.

CASE STUDY



Ettridge v The Vermin Board of the District of Murat Bay

[1928] SASR 124



Facts


  • The contactor was engaged by the principal to construct a fence along a railway line on a schedule of rates basis.
  • During construction, the principal instructed the contractor to deviate from the original line.
  • The contractor refused to construct the fence on the deviated line and abandoned the work, arguing that the contract did not provide the principal with a variations power.

Result


  • The court said that if the principal did not have the contractual power to instruct a variation, then it had repudiated the contract by insisting that the contractor depart from the original line.
  • As a result, the contractor was entitled to terminate the contract.