GLOSSARY TERM  
  Extension of Time (EOT)  
 
  DESCRIPTION  
  Where the Contractor is delayed in performing Works by a specified event of delay, the Contractor may be entitled to an extension equivalent to that delay, to the Date for Practical Completion and potentially other Milestones or the Sunset Date. Usually the Contractor will need to comply with a prescribed process to claim the extension and the extension may be reduced where there is a Concurrent Delay.